Portland Cement Concrete Pavement

420.12 Surface Tests.
The surface of the finished pavement shall be tested and be within the tolerances specified in Article 407.09 and as follows:

Testing with a profilograph for the first several days of paving following initial start up or after a long shutdown period shall be performed as soon as the concrete has cured sufficiently to permit the testing.

When the average profile index for the entire project length does not exceed 67 mm/km (4.25 inch/mile), and no 160 m (0.1 mile) section has a profile index exceeding 160 mm/km (10 inches/mile), the contract unit price shall be increased according to the following Price Adjustment Schedule. When the profile index for a 160 m (0.1 mile) section does not exceed 160 mm/km (10 inches/mile) payment will be made at the contract unit price for that section. When the profile index for a 160 m (0.1 mile) section exceeds 160 mm/km (10 inches/mile) but does not exceed 235 mm/km (15 inches/mile) the contract unit price for that section will be reduced according to the following Price Adjustment Schedule.

PRICE ADJUSTMENT SCHEDULE

Profile Index for Entire Project


mm/km (inch/mile)


Percent of Unit Bid Price
36 (2.25) or less
over 36 (2.25) to 53 (3.25)

103
over 53 (3.25) to 67 (4.25)

102

101

Profile Index for 160 m (0.1 mile)


Section, mm/km (inch/mile)


Percent of Unit Bid Price
over 67 (4.25) to 160 (10)

100
over 160 (10) to 175 (11)

98
over 175 (11) to 190 (12)

96
over 190 (12) to 205 (13)

94
over 205 (13) to 220 (14)

92
over 220 (14) to 235 (15)

90
over 235 (15)

Corrective work required

Membrane curing damaged during the testing operations shall be repaired by the Contractor, at his/her own expense, as directed by the Engineer.

On all areas where corrective grinding is done, the Contractor shall apply, at his/her own expense, a protective coat according to Article 420.21.

Curing and protective covers if used, shall be removed from the pavement for the required profilograph and straightedge measurements and properly replaced when the testing is completed according to Article 1020.13(b).