401.xx
Pavement Smoothness.
The
final pavement surface shall be evaluated for smoothness using a Class I or
Class II profiler as defined by ASTM E950(94). Smoothness measurements will be
expressed in terms of the International Roughness Index (IRI) as defined by the
World Bank, in units of meters/kilometer (inches/mile).
Lot
Size.
Lot
size for smoothness will be 1000 lane-meters (5000 lane-feet). A sublot will
consist of 200 lane-meters (1000 lane-feet). One sublot per lot will be tested
for smoothness. Partial lots will be included in the previous lot if less than
one-half the size of a normal lot; if greater than one-half the normal lot size,
it will be tested as a separate lot.
Testing.
Testing
will be performed by the Department as soon as possible following completion of
the surface pavement. Sublot locations will be determined randomly by the
Engineer. Sections to be excluded from testing include the
following:
Bridge decks and joints (no smoothness measurements will be taken within
50 meters (150 feet) of bridge joints)
Acceleration and deceleration lanes
Shoulders and ramps
Side streets and roads
Immediately prior to testing, the Contractor shall sweep the pavement to
remove all foreign debris. The Contractor will provide the necessary traffic
control to protect Department personnel performing the smoothness measurements.
Where practical, the pavement striping will be used as a reference line
while performing smoothness measurements. Where this is not possible, the
Contractor shall provide reference lines on the pavement as directed by the
Engineer. Each sublot shall have two measurements made in each wheelpath. The
average of the four measurements will determine the smoothness for that lot.
Pay
Adjustment Criteria. Pay
adjustments will be as follows:
Table___-Interstate
highways
IRI
- m/km (in/mile)
Pay Factor
<=
0.552 (35.00)
1.05
0.947
(60.00)
1.00
1.26
(80.00)
0.75
>1.26
(80.00)
Rejected
For IRI values between those listed in the table, the pay factor shall be
determined by the following formula (based on units of
inches/mile):
Pay Factor = 1.05 - (4.2164066E-13*IRI 6.2279)
Table__- Non-Interstate
IRI
m/km (in/mile)
Pay Factor
<=
0.710 (45.00)
1.05
1.105 (70.00)
1.00
1.578 (100.00)
0.75
>1.578 (100.00)
Rejected
For IRI values between those listed in the table, the pay factor shall be
determined by the following formula (based on units of
inches/mile):
Pay Factor = 1.05 - (2.692214E-11*IRI ^ 5.023506)
Computation
of Smoothness Pay Adjustment:
PA = (PF-1.0)(Q)(P)
where:
Q = Quantity of surface course for the project (excluding shoulders, side
streets, bridge decks, ramps, acceleration and deceleration lanes)
PF = Average smoothness pay factor for the project
P = Contract unit price for surface pavement
PA = pay adjustment
No negative pay factors or remedial action
will be enforced in 1999.
Unacceptable
Work. In the event that any lot is found to
have an IRI value exceeding the rejection limit, the Contractor shall take
whatever remedial action is required to correct the pavement surface in that lot
at no additional expense to the Department. Such remedial action may incude but
is not limited to removal and replacement of the unacceptable pavement. In the
event remedial action is necessary, the Contractor shall submit a written plan
to the Engineer outlining the scope of the remedial work. This plan must be
approved by the Engineer before the remedial work can begin. Following remedial
work, the lot shall be retested, and will be subject to the specification limits
listed above. The resulting pay factor, if within the acceptable range, will be
used in the final pay adjustment calculation for the
project.
Localized surface tolerance defects will be subject to the provisions
outlined in section 401.111 Surface Tolerances.