NEW JERSEY

 

 

DIVISION 300 - BASE COURSES

 

                         SECTION 305 - BITUMINOUS‑STABILIZED BASE COURSE

 

305.11  Surface and Thickness.

The surface will be tested using a Straightedge at selected locations.  The variation of the surface, from the testing edge of the Straightedge, between any two contacts with the surface, shall at no point exceed 10 millimeters.  All humps or depressions exceeding 10 millimeters shall be corrected by removing defective work and replacing it with new material.

The thickness requirements shall be as specified in Subsection 404.20.

      

                                       SECTION 306 - CONCRETE BASE COURSE

 

306.04  Construction Requirements.

The surface upon which the concrete base course is to be constructed shall be prepared in accordance with Section 209.

Preformed expansion joint filler, 13 millimeters thick, shall be placed around inlets, manholes, and other similar structures projecting through the base course.

The concrete base course shall be constructed in accordance with Section 405 except as follows:

1.    Joints.  Transverse contraction joints are required and shall be coincident with the transverse expansion joints in adjacent concrete surface course.  In addition, one or more transverse contraction joints, spaced equidistantly not less than 4 meters or more than 6 meters apart, are to be installed between the above joints.  Elsewhere, contraction joints are to be installed at 4.5-meter intervals.

No transverse or longitudinal expansion joints are required.

When the base course is not constructed full width in one operation or when placing of concrete is temporarily discontinued, it shall be finished against a vertical form or bulkhead, and when resumed, the form or bulkhead shall be removed and the concrete shall be placed against the previously finished concrete.

2.    Surface Finish.  The concrete base course may be hand finished.  The surface shall be rough broomed.  Edges need not be rounded.

3.    Curing.  If liquid curing compound is used, it shall be removed prior to surfacing with bituminous concrete.

4.    Surface Tolerance.  The surface will be tested using a Straightedge at randomly selected locations.  The variation of the surface, from the testing edge of the Straightedge, between any two contacts with the surface, shall at no point exceed 10 millimeters.  Surface variations which exceed 10 millimeters shall be corrected.

5.    Thickness Requirements.  The requirements of Subsection 405.21 do not apply.

6.    Slip‑Form Paving.  Subject to a demonstrated ability to adapt slip‑form paving methods to the Department's pavement design, the concrete base may be constructed, without the use of fixed forms, in accordance with Section 405 and the following:

a.     After the subbase has been placed and compacted to the required density, the areas which support the paving machine and the areas on which the base is to be constructed shall be graded to the proper elevation.  If the density of the subbase is disturbed by the grading operations, it shall be recompacted before concrete is placed.  The subbase shall be constructed in advance of placing of the concrete for at least the distance required for an average day's paving.  If any traffic is permitted to use the prepared subbase, the subbase shall be checked and corrected immediately prior to the placing of the concrete.

b.    The concrete shall be placed for the full depth of the slab with a slip‑form paver designed to spread, consolidate, screed, and float-finish the concrete in one pass of the machine, or the concrete may be placed in two layers with a mechanical spreader and then struck off, consolidated, screeded, and float‑finished with a slip‑form paver designed for this purpose.  By either method, the concrete shall be finished in such a manner that a minimum of hand finishing is necessary to provide a dense and homogeneous base.  The machine shall vibrate the concrete for the full width and depth of the base.

c.     Reinforcement, if specified, shall be placed in the plastic concrete after spreading by mechanical or vibratory means.

d.    Any edge slump of the concrete, exclusive of edge rounding, in excess of 6 millimeters, shall be corrected before the concrete has taken its initial set and operations shall be modified to prevent recurrence.

e.     Alignment and grade shall be controlled by an automatic sensing device in continuous contact with a sensing guide.

f.     The concrete shall be placed at a uniform consistency as specified in Section 914, Table 914-1.

g.     The slip‑form paver shall be operated with a continuous forward movement, and all operations of mixing, delivering, and spreading concrete shall be so coordinated as to provide uniform progress, with stopping and starting of the paver held to a minimum.  All vibrations shall automatically cease when the forward movement of the paving machine is stopped.  No tractive force shall be applied to the machine except that which is controlled from the machine.

h.     In order that the concrete may be properly protected against the effects of rain before the concrete is sufficiently hardened, materials shall be made available at all times for the protection of the edges and surface of the unhardened concrete.  Such protective materials shall consist of standard metal forms or wood planks having an actual thickness of not less than 40 millimeters and a minimum actual width of 12 millimeters less than the thickness of the concrete at its edge, for the protection of the edges, and covering material such as burlap or cotton mats, curing paper, or plastic sheeting material for the protection of the base course.  When rain is imminent, all paving operations shall stop and all available personnel shall begin placing forms against the sides of the base course and covering the surface of the unhardened concrete with the protective covering.

 

 

DIVISION 400 - SURFACE COURSES

 

 

                      SECTION 404 - BITUMINOUS CONCRETE SURFACE COURSE

 

404.19  Surface Requirements.

A.    Payment Reductions for New Construction, Reconstruction, or Dualization Projects.

1.    Permissible Surface Variations.  The bituminous concrete surface course will be tested with a rolling Straightedge that automatically marks, in colored dye, the length of surface variations which exceed a tolerance of 3 millimeters in 3 meters, in accordance with the following:

a.     The bituminous concrete surface course placed in the traveled way at locations indicated in the Special Provisions shall be constructed so that when tested in accordance with Subpart A.3 below.  The measured length of lot exceeding 3 millimeters tolerance shall not exceed 1.3 percent.

b.    The bituminous concrete surface course placed in areas other than those specified in the Special Provisions will be tested for acceptance in accordance with Subpart A.4 below.  The measured length of such areas exceeding the 3 millimeters tolerance shall not exceed 3.5 percent.  The number, length, and location of Straightedge tests undertaken to determine conformity in such areas will be at the sole discretion of the Engineer.

2.    Control Testing.  Control testing during placement shall be conducted as may be necessary to ensure compliance with the specified surface requirement.

3.    Surface Acceptance Plan.  Any required sweeping of the surface prior to acceptance testing shall be performed.

Conformance to the surface tolerance for bituminous concrete placed at the locations specified in Subpart A.1 will be determined in lots, each lot being equal to the total number of megagrams of mixture accepted and placed each production day, less the weight of  such mixture placed in areas other than those specified in Subpart A.1.  When the weight of the surface course placed in areas other than those specified in Subpart A.1 cannot be readily determined from weigh tickets and other records, it shall be calculated based on the square meters of such areas paved on the given day, the specified thickness, and the average mix weight per millimeter thick per square meter.

The acceptance of a lot will be based on the percentage of the total length of the lot having surface variation exceeding 3 millimeters in 3 meters, this percent noncompliance being defined as the lot percent defective length.  Lot percent defective length will be computed by adding the lengths, to the nearest 0.3 meter, of individual surface defects exceeding the specified tolerance, dividing this sum by the total length tested, and multiplying by 100 to convert to percent.

The full extent of the lot will be tested in the longitudinal direction.  The transverse location of the test will be in the wheelpaths of vehicle travel, defined as the two imaginary lines located approximately 1 meter on each side of the centerline of the lane and extending for the full length of the lane.  The wheelpath of the test will be determined randomly and varied every 90 to 120 meters.

The minimum number of full-length tests required to determine the lot percent defective length is shown in Table 404-2.  The 25 percent sampling plan, wherein the number of tests is at least equal to one-fourth of the number of wheelpaths in a day's production, will be used initially.  The bituminous concrete surface course will be accepted when the lot percent defective length is equal to or less than 1.0 based on the 25 percent sampling plan.  If a lot percent defective length of 1.1 to 3.4 is indicated by the tests of the 25 percent sampling plan, additional tests will be performed such that the total number of tests performed equals that shown for the 50 percent sampling plan.  If the lot percent defective length in the 25 to 50 percent sampling plan exceeds 3.4, the full length of each wheelpath will be tested.

 

Table 404-2 Surface Acceptance Testing Schedule

 

 

Sampling

Plan

 

Corresponding Number of

Wheelpaths to be Tested

 

Lot Percent

Defective

Length

Measured

 

Reduction

or Retest

Requirement

 

 

 

One

Lane

 

Two

Lanes

 

Three

Lanes

 

Four

Lanes

 

 

 

 

25%

see 50%

Sampling

Plan

1

2

2

0 to 1.0

 

 

1.1 to 3.4

3.5 or more

None

 

 

Perform 50% Testing

Test each wheelpath

 

50%

 

1

 

2

 

3

 

4

 

0 to 3.4

3.5 or more

 

As per Table 404-3

Test each wheelpath

 

100%

 

2

 

4

 

6

 

8

 

All values

 

As per Table 404-3

 

When more than one test is specified in Table 404-2, the initial and intermediate transverse locations of each test will be determined randomly.  In no case will exact duplicate tests be performed.  When testing of all wheelpaths is specified, intermediate transverse variation of the individual tests will not be made.  The results of preceding tests will no be included in the computation of lot percent defective length when application of the 100 percent sampling plan is indicated.

Tests may be performed beyond the minimums specified in Table 404-2.  In addition to the tests run on randomly selected sites, any area which appears defective may be tested including a previous day's production which is damaged by construction.

If the lot percent defective length is 1.4 to 3.4 inclusive and if the Contractor elects not to remove and replace the bituminous concrete surface course, the lot will be accepted upon written request provided that payment for the lot is reduced in accordance with Table 404-3.

 

Table 404-3 Reduction per Lot Due to Nonconformance

to Surface Requirements

 

Lot Percent

Defective Length

 

 

 

Reduction

per Lot, Percent

   0 - 1.3

1.4 - 2.3

2.4 - 3.4

 

None

12

30

 

If the lot percent defective length exceeds 3.4, any or all of the material in the lot may be directed to be removed, replaced, and retested for acceptance.  If the material is permitted to remain in place, payment will not be made for that quantity of material.

4.    Other Testing.  The paving operation is acceptable if the percent defective length of the bituminous concrete surface course does not exceed 3.5.  If the percent defective length exceeds 3.5, the Engineer may direct that paving operations be discontinued until mutually acceptable paving methods and/or equipment are used.

Additional compensation, extension of Contract time, or other concessions will not be granted because of revised methods or equipment necessary to produce a bituminous concrete surface in conformity with the specified surface requirements.

B.    Payment Reductions for Resurfacing or Widening Projects.

1.    Permissible Surface Variations.  The bituminous concrete surface course will be tested with a rolling Straightedge that automatically marks, in colored dye, the length of surface variations which exceed a tolerance of 3 millimeters in 3 meters, in accordance with the following:

a.     The bituminous concrete surface course placed in the traveled way at locations indicated in the Special Provisions shall be constructed so that when tested in accordance with Subpart B.3 below.  The measured length of lot exceeding the 3 millimeters tolerance shall not exceed 3.5 percent.

b.    The bituminous concrete surface course placed in areas other than those specified in the Special Provisions will be tested for acceptance in accordance with Subpart A.4 above.  The measured length of such areas exceeding the 3 millimeters tolerance shall not exceed 3.5 percent.  The number, length, and location of Straightedge tests undertaken to determine conformity in such areas will be at the sole discretion of the Engineer.

2.    Control Testing.  Control testing during placement shall be conducted as may be necessary to ensure compliance with the specified surface requirement.

3.    Surface Acceptance Plan.  Any required sweeping of the surface prior to acceptance testing shall be performed.

Conformance to the surface tolerance for bituminous concrete will be determined in lots.  Each lot will generally be 400 meters long and one lane wide, the latter dimension being determined from the Plans.

The specific limits of each lot will be established by starting at one end of the Project and progressing towards the other in 400-meter increments in the direction of the traffic.  When this procedure results in a remaining pavement length of 300 meters or less, that length of pavement shall be included in and become part of the immediately preceding lot.  If the pavement remainder is greater than 300 meters, it shall be considered a separated lot.

The acceptance of a lot will be based on the percentage of the total length of the lot having surface variation exceeding 3 millimeters in 3 meters, this percent noncompliance being defined as the lot percent defective length.  Lot percent defective length will be computed by adding the lengths, to the nearest 0.3 meter, of individual surface defects exceeding the specified tolerance.  Dividing this sum by the total length tested, and multiplying by 100 to convert to percent.

The full extent of the lot will be tested in the longitudinal direction.  The transverse location of the test will be in the wheelpaths of vehicle travel, defined as the two imaginary lines located approximately 1 meter on each side of the centerline of the lane and extending for the full length of the lane.  In addition to the scheduled lot acceptance tests, any previously tested lot which is damaged by construction operations may be retested.

The rolling Straightedge will not be used immediately adjacent to or over manholes, utility openings, or similar structures which, in the opinion of the Engineer, have a significant and unavoidable adverse impact on achievable smoothness.

If the lot percent defective length is 3.5 or more, the bituminous concrete surface course shall be removed and replaced or may be accepted upon written request provided that payment for the lot is reduced by 20 percent.

The Engineer may test the bituminous concrete surface course with a response type ride meter prior to performing lot acceptance testing with the rolling Straightedge.  If, in the opinion of the Engineer, such ride meter tests indicate, to a substantial certainty, that the lot percent defective length does not exceed the acceptable value of 3.5, the lot will be deemed in compliance with surface requirements.  If the Engineer judges the ride meter tests to be inconclusive, the specified schedule of rolling Straightedge tests will be performed and the lot acceptance decision grounded on those results.

The decision to undertake any optional testing with the ride meter, the specific conduct of the ride meter testing, and the interpretation of the results shall exclusively be the province of the Engineer.

If the lot percent defective length exceeds 3.5, the Engineer may direct that paving operations be discontinued until mutually acceptable paving methods and/or equipment are used.

Additional compensation, extension of time, or other concession will not be granted because of revised methods or equipment necessary to produce a bituminous concrete surface in conformity with the specified surface requirements.

C.    No Payment Reductions.

1.    Permissible Surface Variations.  The bituminous concrete surface course will be tested with a rolling Straightedge that automatically marks, in colored dye, the length of surface variations which exceed a tolerance of 3 millimeters in 3 meters.

2.    Control Testing.  Control testing during placement shall be conducted as may be necessary to ensure compliance with the specified surface requirement.

3.    Surface Acceptance Plan.  Any required sweeping of the surface prior to acceptance testing shall be performed.

The bituminous concrete surface course will be tested for acceptance in accordance with Subpart A.4 above.  The measured length exceeding the 3-millimeter tolerance shall not exceed 3.5 percent.  The number, length, and location of Straightedge tests undertaken to determine conformity will be at the sole discretion of the Engineer.

The percentage of surface variations in noncompliance is defined as the percent defective length which will be computed by adding the lengths, to the nearest 0.3 meter, of individual surface defects exceeding the specified tolerance, dividing this sum by the total length tested, and multiplying by 100 to convert to percent.

 

 

                                   SECTION 405 - CONCRETE SURFACE COURSE

 

405.15  Surface Requirements.

A.    Permissible Surface Variations.  The surface of the concrete will be tested with a rolling Straightedge that automatically marks, in colored dye, the length of surface variations which exceeds a tolerance of 3 millimeters in 3 meters.

Concrete placed on a new mainline shall be so constructed that, when tested in accordance with Subpart B below, the measured length of lot exceeding the specified 3-millimeter tolerance shall not exceed five percent.

Concrete placed in non-mainline areas of the Project or constructed adjacent to an existing roadway, for the purpose of widening, will be tested in accordance with Subpart C below.

B.    Surface Compliance Plan.  Prior to acceptance testing and notching of the expansion joint filler paper necessary to permit passage of the Straightedge, any required sweeping of the surface shall be performed as part of the work.

Conformance to the surface tolerance will be determined in lots, each lot being equal to the number of square meters of concrete surface placed in each production day.

The compliance of a lot will be determined from the percentage of the total length of the lot having surface variation exceeding 3 millimeters in 3 meters, this percent noncompliance being defined as the lot percent defective length.  Lot percent defective length is computed by adding the lengths of individual surface defects exceeding the specified tolerance, dividing this sum by the total length tested, and multiplying by 100 to convert to percent.

The full extent of the lot will be tested in the longitudinal direction along the wheelpaths, defined as the two imaginary lines located approximately 900 millimeters on each side of the center of the lane and extending for the full length of the lane.  The wheelpath of the test will be determined randomly and varied every 90 to 120 meters.

The minimum number of full-length tests required to determine the lot percent defective length is given in Table 405-1 below.  The 25 percent sample plan, wherein the number of tests is at least equal to one-fourth of the number of wheelpaths in a day's production, will be used initially.  Final compliance may be based on the results of the 25 percent sampling except that if the lot percent defective length exceeds 13.9, each wheelpath will be tested.

When more than one test is specified in Table 405-1 below, the initial and intermediate transverse locations of each test will be determined randomly.  Exact duplicate tests will not be performed.  When testing of all wheelpaths is specified, no intermediate transverse variation of the individual tests will be made.  The results of preceding tests are not to be included in the computation of lot percent defective length when application of the 100 percent sample plan is indicated.

In addition to the minimum number of tests specified in Table 405-1 below and run on randomly selected sites, any area which appears defective may be tested including a previous day's production which is damaged by construction operations.

If the lot percent defective length is 5.1 to 13.9 inclusive, the lot shall be removed and replaced or the lot may be accepted upon written request provided that the lot is reduced in accordance with Table 405-2 below.

 

Table 405-1 Surface Acceptance Testing Schedule

 

 

Sampling

Plan

 

Corresponding Number Tests

 

Lot Percent

Defective

Length

Measured

 

Reduction

or Retest

Requirement

 

 

 

One

Lane

 

Two

Lanes

 

Three

Lanes

 

Four

Lanes

 

 

 

 

25%

1

1

2

2

0 to 13.9

14.0 or more

As per Table 405-2

Test each wheelpath

 

100%

 

2

 

4

 

6

 

8

 

All values

 

As per Table 405-3

 

 

 

Table 405-2 Reduction Per Lot Due to Nonconformance

to Surface Requirements

 

Lot Percent

Defective Length

 

 

 

Reduction

per Lot, Percent

  0 - 5.0

 5.1 - 11.0

11.1 - 13.9

 

None

2

5

 

If the lot percent defective length exceeds 13.9, any or all of the concrete in the lot may be directed to be removed, replaced, and retested for acceptance.  If the concrete is allowed to remain in place, the lot quantity will be reduced by 16 percent.

C.    Other Testing.  The riding surface of non-mainline surface, bridge approach and transition slabs, and lanes constructed for the purpose of widening are not subject to the foregoing surface acceptance requirements.

However, the riding surface of any or all portions of the traveled way of the Project (including, but not limited to, such areas as ramps, acceleration or deceleration lanes, and lanes added to widen an existing roadway) may be tested to determine the adequacy of the paving methods and equipment.  The paving operation is acceptable if the riding surface is in substantial conformity with a 3 millimeters in 3 meters surface tolerance.  If the paving operation is unacceptable, the particular placement operation involved shall be discontinued until mutually acceptable methods or equipment are used.

Additional compensation, extension of Contract Time, or other concession will not be allowed because of revised methods or equipment necessary to produce substantial conformity with a 3 millimeters in 3 meters surface tolerance.

D.   Surface Remedial Measures.  Correction of surface by grinding and resubmission for testing may be permitted provided that correction does not require removal of more than 6 millimeters of concrete from the surface.  Grinding shall be performed with equipment specifically designed for the purpose and shall employ either a diamond-studded drum or stacked-blade-type cutting head.  The texture depth in the ground areas shall be similar to that of the adjacent surface.  All ground areas shall be neat areas of uniform appearance.  When use of such remedial grinding procedures is requested, a plan shall be submitted in writing setting forth the intended limits of the surface restoration and a complete description of the methods and equipment proposed for use.