DIVISION 500 - BRIDGES AND STRUCTURES
SECTION 501 - CONCRETE STRUCTURES
501.16 Concrete Deck Surface Requirements.
A. Permissible Surface Variations. The surface of
concrete bridge deck slabs will be tested with a rolling Straightedge that
automatically marks, in colored dye, the length of deck surface variations
which exceed a tolerance of 3 millimeters in 3 meters.
Deck slabs which are required to be struck and finished
with a self-propelled finishing machine shall be so constructed that, when
tested in accordance with Subpart C below, the measured length of lot exceeding
the specified 3 millimeters in 3 meters tolerance shall not exceed 8.9 percent
as specified in Subpart E, Table 501-2, Schedule A below.
When manual strike-off and finishing is permitted and the
option for manual methods is used, the deck slab shall be so constructed that
the measured length of lot exceeding the specified 3-millimeter tolerance shall
not exceed 19.9 percent as specified in Subpart E, Table 501-2,
Subschedule B1 below.
If the option to use a self‑propelled finishing
machine is selected when manual strike-off and finishing is permitted, the deck
slab shall be so constructed that the measured length of lot exceeding the
specified 3 millimeters tolerance shall not exceed 13.9 percent as specified in
Subpart E, Table 501-2, Subschedule B2 below.
B. Control Testing. Deck slab surfaces
shall be systematically checked during placement to correct surface
irregularities while the concrete is in a workable condition.
Such systematic control testing shall be performed as
follows:
1. After the
intended final pass with the finishing machine or other strike-off, the deck
surface shall be checked with a metal Straightedge operated parallel to the
centerline of the bridge. Surface
variations from the testing face of the Straightedge shall be corrected before
the concrete sets. Major deviations shall
be corrected by the finishing machine or other strike-off, while minor
deviations may be corrected by the use of a straightedge or float. The addition of water to the surface of the
concrete to assist in finishing operations will not be permitted.
2. The specific
conduct of the control testing, including the number and location of
Straightedge checks, shall be entirely the province of the Contractor. However, it is suggested that the checking
operation progress in successive 1.5-meter longitudinal increments, with at
least one full‑slab length straightedge check being made within the
transverse limits of each of the designated lanes of traffic.
C. Acceptance Testing. Conformance to the
surface tolerance for concrete deck slabs will be determined in lots, each lot
being equal to the number of cubic meters of deck concrete placed in the
designated lanes of traffic in each production day. Such lot quantity will be calculated using the specified nominal
deck thickness and excludes the quantity of concrete placed in haunches, end
dams, and diaphragms. For the second
course of the two-course deck slab construction, such lot quantity will be
calculated using the specified nominal thickness of the latex modified concrete.
The acceptance of a lot is based on the percentage of the
total length of the lot having surface variation exceeding 3 millimeters in 3
meters, this percent noncompliance being defined as the Lot Percent Defective
Length. Lot percent defective length is
computed by adding the lengths of individual surface defects exceeding the
specified tolerance, dividing this sum by the total length tested, and
multiplying by 100 to convert to percent.
The full extent of the lot will be tested in the
longitudinal direction. The transverse
location of the test generally is in the wheelpaths of vehicle travel, defined
as the two imaginary lines located approximately 915 millimeters on each side
of the centerline of the lane and extending for the full length of the lane.
The minimum number of full‑length tests required to
determine the lot percent defective length is equal to the total number of
wheelpaths in the lot. The number of
tests performed beyond this minimum, if any, and their location, are at the
option of the Engineer.
When the lot percent defective length of a deck slab
exceeds the value specified in the applicable paragraph of Subpart A above but
is less than 25 in the case of a machine‑finished deck or 35 in the case
of a manually finished deck, and if the slab is not removed and replaced, the
lot may be accepted upon written request provided that payment for the lot is
adjusted in accordance with Subpart E, Table 501-2 below.
If the lot percent defective length equals or exceeds 25 on
any machine finished deck (irrespective of whether such machine finishing was
required or optional) or 35 on a manually struck and finished deck, the
Engineer may order any or all of the concrete in the lot to be removed,
replaced, and retested for acceptance.
If the Engineer allows the concrete to remain in place, payment for the
lot will be reduced by 15 percent.
Subpart E, Table 501-2 does not apply to the second course
of two-course deck slab construction.
If the lot percent defective length equals or exceeds 20 on the
finished second courses deck slab, the Engineer may order any or all of the
concrete in the lot to be removed, replaced, and retested for acceptance. If the Engineer allows the concrete to
remain in place, payment for the lot will be reduced by 15 percent.
D. Cessation of Deck Concreting. The Resident
Engineer reserves the right to reject bridge deck construction methods or
equipment which do not result in surfaces which are in substantial conformity
with the 3 millimeters in 3 meters surface tolerance. The deck will be considered in substantial conformity with the
required surface tolerance only if the lot percent defective length does not
exceed the value specified in the applicable paragraph of Subpart A above.
The continued use of methods and equipment which result in
a lot percent defective length of 20 or more on any machine finished deck slab
or 35 or more on any manually struck and finished deck will not be
permitted. If these limitations are
exceeded, deck placement and finishing shall be discontinued until other
methods or equipment are proposed for trial and submitted in writing for
approval. Approval of this revised plan
of operations does not relieve responsibility for the satisfactory performance
of the revised method or equipment.
Additional compensation, extension of Contract Time or
other concession will not be granted because of revised methods or equipment
necessary to produce deck slabs in substantial conformity with the 3
millimeters in 3 meters surface tolerance.
E. Surface Remedial Measures. Regardless of the
overall surface conformity of a lot of bridge deck concrete, if surface
deviations have a detrimental effect on deck drainage or reinforcement steel
cover, the Engineer may require appropriate remedial measures to restore any or
all of the deck slab surface to the required grades and surface tolerance. When
such remedial procedures are ordered by the Engineer, a plan shall be
submitted, setting forth the intended limits of the surface restoration and a
complete description of the methods, equipment and materials proposed for use.
Following satisfactory completion of the surface
restoration measures to the bridge slab, the lot containing the affected area
shall be retested.
Additional compensation, extension of Contract Time or
other concessions will not be granted for any surface restorations ordered.
Table 501-2 Reduction Per Lot of Deck Slab
Concrete Due to
Nonconformance with Surface Requirements
|
Schedule A Machine
Finishing Required |
|
Schedule B Machine
Finishing Optional |
|||||||
|
|
|
|
Subschedule B1 Manual
Finishing |
Subschedule B2 Machine
Finishing |
|||||
|
Lot Percent Defective Length |
Reduction Per Lot, Percent |
|
|
|
|
Lot Percent Defective Length |
Reduction Per Lot, Percent |
Lot Percent Defective Length |
Reduction Per Lot, Percent |
|
0-8.9 |
none |
|
|
|
|
0-19.9 |
none |
0-13.9 |
none |
|
9.0-13.9 |
1.0 |
|
|
|
|
20.0-27.0 |
2.5 |
|
|
|
14.0-24.9 |
7.0 |
|
|
|
|
27.1-34.9 |
7.0 |
14.0-24.0 |
7.0 |
Remedial measures will not be required for the surface of
the first course construction for high spots which do not exceed the prescribed
grade by more than 6 millimeters in 3 meters.