DIVISION 7
CONCRETE
PAVEMENTS AND SHOULDERS
_______________
Portions of this
specification not related to final
surface testing were deleted. The
entire specification is available at :
http://www.doh.dot.state.nc.us/preconstruct/highway/dsn_srvc/specifications/english/
710-7 FINAL SURFACE TESTING.
Acceptance testing of the longitudinal profile of the finished
pavement surface shall be performed by the Contractor in the presence of the
Engineer in accordance with these provisions.
A Rainhart Profilograph (Model 1, No. 860) shall be furnished and
operated by the Contractor to determine and record the longitudinal profile on
a continuous graph (Profilogram) for acceptance testing of the pavement. Profiles shall be taken the day after the
pavement has been placed except where impractical, but in no event later than
72 hours following placement of the pavement.
The Profilograph shall be towed, pushed manually, or otherwise
moved over the pavement at a speed not exceeding 2 miles per hour. The propulsion vehicle shall have a gross
weight not exceeding 1,000 pounds and shall have been approved by the
Engineer. Profiles shall be taken with
the recording wheel parallel to and approximately 3.5 ft. inside the two outer edges
of the travel lanes and at the location of each longitudinal joint. Profiles will be taken over the entire
length of through lane and ramp pavement exclusive of structures and approach
slabs. Additional profiles shall be
taken only to define the limits of an out-of-tolerance surface variation. Upon completion of each day's testing, the
Profilograms shall be submitted to the Engineer for analysis and will be
retained by the Engineer.
At the beginning and end of each day's testing operations, and
at such other times as determined necessary by the Engineer, the Profilograph
shall be operated over a calibration strip so that correct operation of the
Profilograph can be verified by the Engineer.
The calibration strip shall be a section of pavement selected by the
Engineer. Obstructions of known
dimensions shall be furnished by the Contractor and temporarily installed by
him in the path of the Profilograph.
The Profilograph shall be operated by the Contractor in the same manner
as it is operated over pavement outside of the calibration strip.
The Profilogram shall be plotted at a horizontal scale of 25
feet per inch with the vertical scale plotted at a true scale. Station numbers and reference lines shall be
recorded on the Profilograms, and distances between reference locations shall
not exceed 200 feet.
The profile index will be determined by the Engineer in
accordance with the procedure titled "Determination of Profile
Index". Copies of this procedure
can be obtained from the Construction Unit.
The completed concrete pavement surface shall have a profile
index (PI) along any line tested not exceeding 4 inches per mile, as determined
with a 0.20 inch blanking band, over any 600 foot section of pavement. Individual deviations shall not exceed 0.3 inches
over any 25 foot length of the line tested.
In the event the above surface requirements are not met, acceptance will
be made in accordance with Article 105‑3.
Membrane curing compound damaged during acceptance testing
operations shall be promptly repaired by the Contractor.
In the event the Contractor does not produce a pavement surface
that meets the requirements of this article, the Engineer may suspend the
Contractor's operations until such time as the Contractor satisfies the
Engineer, by making necessary adjustments to equipment, methods, or personnel,
that he can produce a pavement surface that will meet these surface
requirements. The use of excessive
grinding, as determined by the Engineer, to meet these requirements will not be
permitted.