(1)
RIDEABILITY
OF FINISHED ASPHALT SURFACE:
This Special Provision will
only apply if the following conditions are met:
(1) A constant speed of fifty
(50) miles per hour can be maintained throughout each section 1 for which
measurements are made.
(2) The segment of roadway
is a minimum continuous length of 0.5 mile (Bridges are considered areas of
discontinuity).
1 Normally a section will be
considered as 1.0 mile in length. However, no measurements will be made on any
section less than 0.5 mile in length. Sections which are less than 1.0 mile,
but are 0.5 mile or greater, normally occur at the end of project.
Subsection 401.27,
"Surface Requirements", of the Standard Specifications shall be
amended for the riding surface as follows. The pavement surface of the lanes
shall be constructed with a satisfactory ride, as determined by the Engineer.
In order to assist the Engineer in making this determination, the Department
shall test the pavement with the Mays Ride Meter.
It is the intent of the
Specification that the smoothest possible ride be achieved during construction.
The roughness shall not exceed 40 inches for each mile of each vehicle lane when
tested in accordance with the "Test Method for Determining Pavement
Roughness with the Mays Ride Meter". When initial measurements are 40
inches per mile or less, payment will be made based on the original contract
unit bid price per ton of asphalt concrete mixture according to the “Schedule
for Adjusted Payment.” The total amount of any increases in payment will be
included as a lump sum to monies due the Contractor.
When the measurements exceed
40 and the Engineer also determines that the pavement does not have an
acceptably smooth ride, the contractor shall correct such sections without
additional compensation. The Engineer may withhold payment (or portion thereof)
for the asphalt concrete mixture until corrections have been made and the
pavement provides an acceptably smooth ride.
The method of correcting the surface
deficiencies shall be approved by the Engineer. No more than 100% of
contract unit price will be paid for sections where corrective work results in
measurements less than 35 inches per mile. In the event that corrections resulting in an acceptably
smooth ride are not made, then a price adjustment will be assessed. Payment
will be made based on the original contract unit bid price per ton of asphalt
concrete mixture according to the “Schedule for Adjusted Payment.” The total
amount of any reduction in payment will be deducted as a lump sum from monies
due the Contractor.
Roughness
(inches per mile)
Price
Adjustment
less than 24 105%
25 - 29 103%
30 - 34 101%
35 – 40 100%
41 – 45 95%
46 – 50 90%
51 – 55 80%
56 and above see
note 2
2 Sections of roadway for
which the roughness per mile is measured at 56 inches per mile and above will be
reviewed on an individual basis. The Department may determine these areas to be
unacceptable, in which case the material shall be removed and replaced or
overlaid with Department approval. Should the Department determine that the
material may remain in place and not overlaid, a price adjustment will be
assessed. For each additional increment of 5 inches per mile of roughness above
55 inches per mile, an additional 10% reduction will be made based on the
contract unit price of asphalt mixture.
(2) RIDEABILITY OF FINISHED
ASPHALT SURFACE:
See Attached Supplemental
Specification dated January
21, 1992 on
page 3. The attached
Supplemental Specification
is amended as follows:
This Special Provision will
only apply if the following conditions are met:
(1) A constant speed of
fifty (50) miles per hour can be maintained throughout each section 1 for
which measurements are made.
(2) The segment of roadway
is a minimum continuous length of 0.5 mile (Bridges are considered
areas of discontinuity).
1 Normally a section will be
considered as 1.0 mile in length. However, no measurements will be
made on any section less
than 0.5 mile in length. Sections which are less than 1.0 mile, but are 0.5
mile
or greater, normally occur at the end of project.
January 21, 1992
Subsection
401.27, “Surface Requirements,” of the Standard Specifications shall be amended
for the riding surface. The relative roughness will be determined in accordance
with the “Test Method for Determining Pavement Roughness with the Mays Ride
Meter” on the existing pavement before any work is performed by the Contractor
and again on the final surface after work is completed. To ensure as smooth a
ride as possible, the original roughness value measured on the existing
pavement for each mile of each vehicle lane shall be improved as shown in the
Acceptable Roughness Specification Table contained in this Special Provision.
Where measurements on the final surface exceed the acceptable limit, the
Contractor shall correct such sections without additional compensation. The
method of correcting the surface deficiencies shall be approved by the
Engineer.
In
the event the corrections are not made, then a penalty will be assessed based
on the original
contract unit price as
follows:
Inches/Miles Over
Acceptable Limit Penalty
1 – 5
5%
6 – 10
10%
11 – 15
15%
16 – 20
20%
21 – 25
25%
26 and above
Replace
The tonnage to be penalized will be based on the original plan quantity as
shown on the Typical
Section. When an acceptable
smooth ride is not obtained as outlined above, the Engineer may withhold
payment ( or portion thereof) for the surface mix until the above corrections
have been made and the pavement provides an acceptable smooth ride. If a
penalty is necessary to be assessed, the total amount of the penalty will be
deducted from monies due the Contractor. See table on following page.
ACCEPTABLE
ROUGHNESS SPECIFICATION TABLE
MAYS
RIDE METER (INCHES/MILE)
ORIGINALROUGHNESS |
FINAL
ACCEPTABLE ROUGHNESS (MAXIMUM) |
ORIGINAL ROUGHNESS |
FINAL
ACCEPTABLE ROUGHNESS(MAXIMUM) |
|
40
or less |
40 |
77 |
65 |
|
41 |
40 |
78 |
65 |
|
42 |
41 |
79 |
66 |
|
43 |
42 |
80 |
66 |
|
44 |
43 |
81 |
66 |
|
45 |
44 |
82 |
67 |
|
46 |
45 |
83 |
67 |
|
47 |
46 |
84 |
68 |
|
48 |
47 |
85 |
68 |
|
49 |
48 |
86 |
68 |
|
50 |
49 |
87 |
69 |
|
51 |
49 |
88 |
69 |
|
52 |
50 |
89 |
69 |
|
53 |
51 |
90 |
70 |
|
54 |
52 |
91 |
70 |
|
55 |
52 |
92 |
70 |
|
56 |
53 |
93 |
71 |
|
57 |
54 |
94 |
71 |
|
58 |
54 |
95 |
71 |
|
59 |
55 |
96 |
72 |
|
60 |
56 |
97 |
72 |
|
61 |
56 |
98 |
72 |
|
62 |
57 |
99 |
72 |
|
63 |
57 |
100 |
72 |
|
64 |
58 |
101 |
73 |
|
65 |
59 |
102 |
73 |
|
66 |
59 |
103 |
73 |
|
67 |
60 |
104 |
73 |
|
68 |
60 |
105 |
73 |
|
69 |
61 |
106 |
74 |
|
70 |
61 |
107 |
74 |
|
71 |
62 |
108 |
74 |
|
72 |
62 |
109 |
74 |
|
73 |
63 |
110 |
74 |
|
74 |
63 |
111 |
74 |
|
75 |
64 |
112 |
74 |
|
76 |
64 |
113
or above |
75 |